CU 3 for 7.15 LTSR


Dennis Haschke

Question

Hello,
we use XA 7.15 LTSR CU2 and we plan to upgrade to 7.15 CU3.
Is it necessary to upgrade all components (license server, pvs, ddc, storefront, vda agent) in a relativly short time range or is it possible to upgrade on one day License Server, another day storefront and so on...…….

Regards
Dennis

Link to comment

4 answers to this question

Recommended Posts

I try this yesterday evening when only some connections are alive…….works.
 

Describes in the article: https://docs.citrix.com/en-us/citrix-virtual-apps-desktops/upgrade-migrate/upgrade.html?_ga=2.147653183.924710991.1551691940-250645343.1542615285

Leaving half of the Controllers active allows users to access the Site. VDAs can register with the remaining Controllers. There may be times when the Site has reduced capacity because fewer Controllers are available. The upgrade causes only a brief interruption in establishing new client connections during the final database upgrade steps. The upgraded Controllers cannot process requests until the entire site is upgraded.

If your Site has only one Controller, it is inoperable during the upgrade.